INDOOR COURT UPDATE
The final arrangements for construction of the 4 indoor courts
are now in place and work will start on site on Tuesday 6th
April.
The contract went out to tender in January and the tender
process was coordinated by the project managing company, Lee West
Associates. Dove Construction were successful in the tender bid
process and we are pleased to say that the tender costs are within
the original forecasted costs of £800K.
Dove Construction, based in Cheltenham, have worked closely with
Summit Structures (who manufacture and provide the fabric frame
structure) on a number of projects and are therefore very familiar
with the requirements of our development.
The confirmation of LTA funding has also been finalised and
there is some very significant positive news to report in that the
ratio of grant to loan funding has been changed.
Our financial projections were based on a grant of £140K and an
interest free loan of £260k. The actual funding offer that we have
received is for a £300K grant and an interest free loan of £100K.
This is a significant improvement and immediately reduces our
annual repayments to the LTA over the 10 year payback period by
£16K.
The construction period is projected to last 25 weeks and we
will have the courts ready at the start of October in time for the
2010-11 winter season. The next consideration is how the club
operates over the next 6 months while the construction is going
on. We will be working closely with the contractors to
minimise any inconvenience to members and will aim to keep members
well informed throughought the construction period.